Project Overview

  • Client: British Gas
  • Contractor: Technical Demolition Services Ltd
  • Location: Gas Works Finmere Road, Eastbourne, BN22 8QL
  • Project Type: Hanger access scaffold for the demolition of an old gas tanker
  • Timescale: 12 weeks
  • Site manager: Peter Chaloner

Scaffolding Requirements

Access scaffold to remove liquid / gas residue before demolition works take place. Safety access platform was also erected which held a rescue winch in case of emergency. Building a hanger scaffold inside a gas tanker for demolition is a complex and highly specialized task that requires attention to safety, precision, and engineering detail. Specialist RAMS, operative training and scaffold design is required for such a project. ACE Scaffolding provide all of this, minus the bespoke scaffold design which is engineered independently.

How we approached this project

1. Planning and Safety Considerations

Before starting, thorough planning is crucial. Given that this is a gas tanker, it’s essential to ensure that it is fully decontaminated to remove any residual gas or flammable materials.

A risk assessment and safety protocols were put in place, including personal protective equipment (PPE) for workers and gas monitoring equipment. The scaffold design and all ACE operatives on site complied with industry regulations.

2. Engineering and Scaffold Design:

The main scaffold is designed as a “hanger scaffold” which means it’s suspended from the structure above rather than built up from the ground. Since the interior of the gas tanker is a confined and curved space, the scaffold needs to be custom-built to fit the internal geometry of the tanker.

Peter and the Technical Demolition team cut a large hole out of the top the tank suitable to fit all scaffold structures and human entry required.

Key design elements include:

  • Suspension Points – Strong and secure points are identified where the scaffold can be safely anchored.
  • Weight Distribution – The scaffold structure itself was carefully calculated by the design engineer to ensure the kentledge holding the scaffold on ground suits the weight of the scaffold entering the tank. This was also must be robust enough to hold operatvies, tools, and debris. Engineers calculate load-bearing capacities for safety.
  • Platform size – The design engineer had to ensure that the hanger scaffold width & length was suitable for ACE operatives to ensure the high level of safety at all times.
Industial Scaffolding Eastbourne British Gas

3. Installation of the Hanger Scaffold (The installation process was as follows):

  • Erection of on ground scaffold structure
  • Installation of kentledge water weights
  • Add water to the 1 tonne kentledge weights
  • Build hanger support scaffold strucutre
  • Erect hanger scaffold
  • Erect rescue platform
  • Install rescue winch

Once the work was complete, all scaffold is dismantled in reverse order. 

Building a hanger scaffold inside a gas tanker for demolition requires a balance of engineering expertise and safety. The scaffold must be strong, stable, and adaptable to the confined nature of the tanker while providing safe access for operatvies to carry out works.

Specialist training: ACE Scaffolding operatives were confined space trained. All scaffolders on site hold CISRS qualifications. 

It was a pleasure working with James Sands (Director), Peter Chaloner (Site Manager) and the team on such an exhilarating project.

The Technical Demolition team were highly organised and professional throughout works.

Ace Scaffolding Utilities British Gas 12

“Breyer Group PLC have been working alongside ACE Scaffolding for the past 2 years. We value our collaboration, their quality of workmanship and professionalism,highly recommended”

Stephen JexSenior Contracts Manager, Breyer Group PLC

“As always, Ace did an ace job for me. Very responsive to all enquiries, good survey with several options for the job and kept me updated on the schedule. All work was done efficiently and tidily.”

John RouseBuilder

“The full package! Great team on site yesterday and a pleasure to work with. I have been very impressed with ACE Scaffolding so far. Keep it up.”

Russell ForderSite Manager, Square One Construction

“Very quick and efficient scaffolding for our works on our house in Brighton. I have recommended them many times to friends and family who have also been very happy with the service.”

Ian WalkerHome Owner

“They listened to how I thought the scaffolding should be built then suggested a far better way of doing it, making my job far safer and easier to perform.”

Ashley BurrowsBuilder

“Very quick and efficient scaffolding for our works on our house in Brighton. I have recommended them many times to friends and family who have also been very happy with the service.”

Ian WalkerHome Owner

“All of the staff, through to the lads on site are very organised and know what they are doing. The price for the job was super competitive and they will be my number one go to in the future.”

Ken MitchellBuilder

“Recently used these guys for a job at my place of work, they were really polite and couldn’t have been better to have around. Super helpful as well and even helped me clean the gutter.”

Alfie AlvarezCommercial Customer

“We have used Ace Scaffolding for the last five years for all our scaffolding works and found them to be reliable and give a good service.”

Howard Building & Maintenance Ltd.Builder

“Ace Scaffolding have once again blown me away with their service, The skill of their tradesmen, the politeness and helpfulness of their tradesmen, and their reliability.”

Ashley BurrowsBuilder
View More Testimonials

Ready to discuss your scaffolding requirements?