Project Overview

  • Client: NHS
  • Contractor: Pattenden Construction
  • Location: Block F, Brighton General Hospital, Elm Grove, BN2 3EW.
  • Project Type: Full independent wrap of building + weather protection.
  • Timescale: 24 weeks
  • Site manager: Tommy Pattenden

Scaffolding Requirements

The NHS saw fit to provide some general maintenance to Block F. This building had been untouched for many years.

Scaffolding erected on site was a full independent wrap which included external birdcages, a small temporary roof covering the independent only, with cladding choice being a full shrink wrap.

Means of access was through a HAKI staircase which included a safety fence on the base lift. There were numerous ladder exists through all lifts to ground level in case of emergency on site.

How we approached this project

1. Planning and Safety Considerations: Before any works started, many pre-site meetings to calculate all the risks had taken place.

We were aware the building was to be kept open on erection and dismantle of the block. Therefor fire exists and doorways had to be kept safe when scaffolding works were taking place.

Site specific RAMS were provided by our H&S team to ensure the building could be live.

Our team were only to work behind barriered off areas which included plenty of signage.

We stuck to a schedule when erecting and dismantling scaffolding per elevation to ensure we wouldn’t affect all areas of the building when working.

Ace Scaffolding Emergency Services NHS Brighton General Hospital Block F 28

2. Engineering and Scaffold Design:

Upon our first survey our surveying team had taken all the building measurements. This was then sent to an independent design company who also attended a site visit.

Our team working alongside the SDL team then discussed and produced the design, load calculations and risk assessment for this project.

The majority of the scaffolding was basic. The main factor to take into consideration here was the wind speeds, it being on the top of a hill only a few miles from the seafront.

Key design elements include:

  • Building survey – The engineer was not given any building documents. Therefor a day’s work was required to survey the full ins and outs of the building.
  • Structure safety – Anchor ties were the tie of choice on site here. The engineer included over 100 ties on site. Ties were pull tested with certificate evidence.  The engineer had to take weather conditions into consideration here. As the area is so close to the seafront.
  • Platform size – The basic independent was always going to be 4 boards wide with X2 inside boards. But there were birdcage scaffolds included, some of which 20 boards wide.
  • Additional structures – A small temporary roof was erected over the top lift of the scaffolding. Due to render works being carried out and a tight schedule to follow the client did not want any hold ups.
Ace Scaffolding Emergency Services NHS Brighton General Hospital Block F 29

3. Installation of scaffold on site (The installation process was as follows):

  1. Making safe working areas
  2. Adding barriers and signage
  3. Erection of the independent scaffold
  4. Erection of birdcage scaffolds
  5. Complete elevations in site required order
  6. Erection temporary roof over independent
  7. Adding ties required by design
  8. Pull testing 5% of ties
  9. Installation of HAKI staircase
  10. Installation of shrink wrap

Once the work was complete, all scaffold is dismantled in reverse order. 

Specialist training: All scaffolders on site hold CISRS qualifications. ACE Advance scaffolding inspector. 

It was a pleasure working with Tommy & Billy Pattenden (Directors) on such a great project. This site is an iconic landmark in the Brighton City. Being opened in September of 1867 this hospital has survived 2 world wars which accommodated many soldiers in those eras.

The Pattenden team working alongside the onsite NHS management team were highly organised and professional throughout works.

Ace Scaffolding Emergency Services NHS Brighton General Hospital Block F 2

“Breyer Group PLC have been working alongside ACE Scaffolding for the past 2 years. We value our collaboration, their quality of workmanship and professionalism,highly recommended”

Stephen JexSenior Contracts Manager, Breyer Group PLC

“As always, Ace did an ace job for me. Very responsive to all enquiries, good survey with several options for the job and kept me updated on the schedule. All work was done efficiently and tidily.”

John RouseBuilder

“The full package! Great team on site yesterday and a pleasure to work with. I have been very impressed with ACE Scaffolding so far. Keep it up.”

Russell ForderSite Manager, Square One Construction

“Very quick and efficient scaffolding for our works on our house in Brighton. I have recommended them many times to friends and family who have also been very happy with the service.”

Ian WalkerHome Owner

“They listened to how I thought the scaffolding should be built then suggested a far better way of doing it, making my job far safer and easier to perform.”

Ashley BurrowsBuilder

“Very quick and efficient scaffolding for our works on our house in Brighton. I have recommended them many times to friends and family who have also been very happy with the service.”

Ian WalkerHome Owner

“All of the staff, through to the lads on site are very organised and know what they are doing. The price for the job was super competitive and they will be my number one go to in the future.”

Ken MitchellBuilder

“Recently used these guys for a job at my place of work, they were really polite and couldn’t have been better to have around. Super helpful as well and even helped me clean the gutter.”

Alfie AlvarezCommercial Customer

“We have used Ace Scaffolding for the last five years for all our scaffolding works and found them to be reliable and give a good service.”

Howard Building & Maintenance Ltd.Builder

“Ace Scaffolding have once again blown me away with their service, The skill of their tradesmen, the politeness and helpfulness of their tradesmen, and their reliability.”

Ashley BurrowsBuilder
View More Testimonials

Ready to discuss your scaffolding requirements?